Contract
$214,000
ex GST
Invoiced to date
$56,200
26% of contract
Fabrication
$56,860
3 fab jobs · cost $37,207
Fabrication return
$19,653
margin 34.6%
Project return
$133,793
contract less fab $37,207 + install $43,000
Fab jobs for this project$23,927 spent to date
| Fab job | Item | Qty | Stage | Due | Material | Value | Cost | Return | Margin |
|---|---|---|---|---|---|---|---|---|---|
| FJ-26-0398 | PAL-2421 Palisade panel 2.4 × 2.1 W-pale, HDG | 38 | Welding & assembly | 12 Nov | Allocated | $22,420 | $14,700 | $7,720 | 34.4% |
| FJ-26-0388 | SLD-GATE-6 Cantilever sliding gate 6.0 × 2.1, HDG | 2 | Complete | 21 Oct | issued | $7,300 | $4,415 | $2,885 | 39.5% |
| FJ-26-0387 | PAL-2421 Palisade panel 2.4 × 2.1 W-pale, HDG | 46 | Complete | 16 Oct | issued | $27,140 | $18,092 | $9,048 | 33.3% |
Invoices & claimsAll invoices
| INV-010862 23 Oct | Hazelmere Logistics Hub — claim 2 (sliding gates) | Overdue | $9,260 |
| INV-010861 16 Oct | Hazelmere Logistics Hub — claim 1 | Paid | $46,940 |
Purchase orders
| PO-26-0520 | Westgate Gate Hardware | Received | $5,128 |