Fence Corporation

FJ-26-0398 · 38 × PAL-2421

Palisade panel 2.4 × 2.1 W-pale, HDG · CI-26-022 Hazelmere Logistics Hub — palisade & sliding gates
Xero · synced 09:14 Demo 05 Nov 2026
Welding & assembly Civil & Industrial
Move to
Value
$22,420
sell to Hazelmere Industrial Pty Ltd
Estimated cost
$14,700
est. margin 34.4%
Cost to date
$1,420
forecast $14,700
Forecast return
$7,720
margin 34.4% · ROI 52.5%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $11,002 reserved now
$11,002$0 —
Labour
17.4 h logged of 25.3 h estimated
$1,571$1,030 $541
Machine time
at the machine's hourly rate
$532$391 $141
Galvanising (outside)
Industrial Galvanizers — billed per load
$1,596$0 $1,596
Total$14,700$1,420
Job detailsCI-26-022 →
Item
PAL-2421 Palisade panel 2.4 × 2.1 W-pale, HDG
Quantity
38
Finish
Hot-dip galvanised
Project
CI-26-022 — Hazelmere Logistics Hub — palisade & sliding gates
Customer
Hazelmere Industrial Pty Ltd
Machine
WB-1
Start / due
29 Oct 2026 → 12 Nov 2026
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
ANG50 Angle 50 × 50 × 5 182.4 m 182.4 — $7.80 $1,423
WPL21 W-pale 2100 galv 836 ea 836 — $11.40 $9,530
WW09 Welding wire ER70S-6 0.9 mm 7.6 kg 7.6 — $6.40 $49
Hours logged17.4 h · labour $1,030 · machine $391
DateWhoOperationMachineHoursLabourMachine
05 Nov 2026 Tama Ngata Welding WB-1 3.5 $214 $98
03 Nov 2026 Josh Taylor Galv prep & touch-up — 3.48 $136 $0
30 Oct 2026 Amir Welding WB-1 3.32 $246 $93
29 Oct 2026 Tama Ngata Welding WB-1 7.13 $435 $200