Welding & assembly Civil & Industrial
Move to
Value
$22,420
sell to Hazelmere Industrial Pty Ltd
Estimated cost
$14,700
est. margin 34.4%
Cost to date
$1,420
forecast $14,700
Forecast return
$7,720
margin 34.4% · ROI 52.5%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $11,002 reserved now | $11,002 | $0 | — |
| Labour 17.4 h logged of 25.3 h estimated | $1,571 | $1,030 | $541 |
| Machine time at the machine's hourly rate | $532 | $391 | $141 |
| Galvanising (outside) Industrial Galvanizers — billed per load | $1,596 | $0 | $1,596 |
| Total | $14,700 | $1,420 |
Job detailsCI-26-022 →
- Item
- PAL-2421 Palisade panel 2.4 × 2.1 W-pale, HDG
- Quantity
- 38
- Finish
- Hot-dip galvanised
- Project
- CI-26-022 — Hazelmere Logistics Hub — palisade & sliding gates
- Customer
- Hazelmere Industrial Pty Ltd
- Machine
- WB-1
- Start / due
- 29 Oct 2026 → 12 Nov 2026
Material — allocated from stock
Hours logged17.4 h · labour $1,030 · machine $391
| Date | Who | Operation | Machine | Hours | Labour | Machine | |
|---|---|---|---|---|---|---|---|
| 05 Nov 2026 | Tama Ngata | Welding | WB-1 | 3.5 | $214 | $98 | |
| 03 Nov 2026 | Josh Taylor | Galv prep & touch-up | — | 3.48 | $136 | $0 | |
| 30 Oct 2026 | Amir | Welding | WB-1 | 3.32 | $246 | $93 | |
| 29 Oct 2026 | Tama Ngata | Welding | WB-1 | 7.13 | $435 | $200 | |