358 mesh short for FJ-26-0406Forrestfield pedestrian gates need 4 sheets — 0 free. PO-26-0532 due 12 Nov.
05 Nov 2026 · 08:05
FJ-26-0397 running lateSecurity posts for Kwinana were due 3 Nov — base plates arrived short.
05 Nov 2026 · 07:40
Surfmist panels short for TreebyLots booked from 16 Nov need 46 more panels than finished stock. FJ-26-0402 is on RF-01.
04 Nov 2026 · 16:20
Quote Q-26-0451 viewedLauren Mitchell (Canning Vale Distribution) opened the quote twice.
04 Nov 2026 · 14:10
FJ-26-0392 complete24 × Flexistep 2-step kits — batch FC-261103-12. Return 46.4%.
03 Nov 2026 · 15:30
PB-01 down for repairPress brake back gauge sensor — back in service Mon 9 Nov.
03 Nov 2026 · 11:00
INV-010862 overdueHazelmere claim 2 was due 3 Nov.
02 Nov 2026 · 09:15
LC-01 factory acceptance signed offFibre laser tube cutter signed off in Foshan. Container ETA Fremantle 4 Dec.
28 Oct 2026 · 17:45
Activity log
Liam O'Connor · Time FJ-26-0400 logged 3.5 h roll forming on RF-0105 Nov 2026 · 09:02
Amir · Fab job FJ-26-0401 moved to Cutting & forming05 Nov 2026 · 08:40
Katie · Purchase order PO-26-0533 drafted — Fasteners WA05 Nov 2026 · 08:05
Sipho Ndlovu · Fab job FJ-26-0393 moved to QC & dispatch — truck to Broome booked Mon04 Nov 2026 · 16:10
Dehan Pretorius · Project CI-26-022 install 70% — north and west boundaries done04 Nov 2026 · 11:30
Amir · Fab job FJ-26-0392 completed — batch FC-261103-1203 Nov 2026 · 15:30
Nikki Chen · Invoice INV-010865 sent to Swan Modular Hire — synced to Xero03 Nov 2026 · 14:00
Katie · Purchase order PO-26-0527 part received — 300 of 400 base plates03 Nov 2026 · 10:15
Craig Hollis · Lot Ellenbrook 6 lots scheduled for next week02 Nov 2026 · 13:20
Dehan Pretorius · Quote Q-26-0457 sent to Malaga Truck Centre02 Nov 2026 · 09:00
Nikki Chen · Invoice Oct claims October lot claims sent to 6 developers — synced to Xero30 Oct 2026 · 16:40
Amir · Fab job FJ-26-0391 completed — 220 Basalt panels into finished stock30 Oct 2026 · 15:10