Fence Corporation

FJ-26-0393 · 14 × FLX-K4

Flexistep stair kit — 4 step · FX-26-010 Flexistep supply — Broome camp
Xero · synced 09:14 Demo 05 Nov 2026
QC & dispatch Urgent Fabrication
Move to
Value
$24,640
sell to Kimberley Site Accommodation
Estimated cost
$10,866
est. margin 55.9%
Cost to date
$2,982
forecast $10,944
Forecast return
$13,696
margin 55.6% · ROI 125.1%
Variance to estimate
−$79
over estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $7,774 reserved now
$7,774$0 —
Labour
24.6 h logged of 24.5 h estimated
$1,519$1,376 $143
Machine time
at the machine's hourly rate
$425$379 $45
Galvanising (outside)
Industrial Galvanizers — billed per load
$1,148$1,227 −$79
Total$10,866$2,982
Job detailsFX-26-010 →
Item
FLX-K4 Flexistep stair kit — 4 step
Quantity
14
Finish
Hot-dip galvanised
Project
FX-26-010 — Flexistep supply — Broome camp
Customer
Kimberley Site Accommodation
Machine
WB-1
Start / due
26 Oct 2026 → 06 Nov 2026
Notes
Truck to Broome booked Mon 9 Nov — Kimberley want them on the first load.
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
CHS34 CHS 33.7 × 2.6 galv 95.2 m 95.2 — $7.20 $685
FX-FIX Flexistep fixing kit 14 kit 14 — $26.00 $364
FX-LEG Flexistep adjustable leg kit 84 ea 84 — $44.00 $3,696
FX-TRD Flexistep tread — galv grating 900 × 250 56 ea 56 — $38.00 $2,128
SHS50 SHS 50 × 50 × 2.0 galv 100.8 m 100.8 — $8.40 $847
WW09 Welding wire ER70S-6 0.9 mm 8.4 kg 8.4 — $6.40 $54
Hours logged24.6 h · labour $1,376 · machine $379
DateWhoOperationMachineHoursLabourMachine
05 Nov 2026 Sipho Ndlovu Packing & dispatch — 2.5 $135 $0
03 Nov 2026 Liam O'Connor Packing & dispatch — 3.19 $179 $0
02 Nov 2026 Josh Taylor Assembly — 5.37 $209 $0
30 Oct 2026 Ben Whitfield Welding WB-1 0.91 $53 $25
28 Oct 2026 Amir Welding WB-1 3.69 $273 $103
27 Oct 2026 Tama Ngata Welding WB-1 2.68 $163 $75
26 Oct 2026 Ben Whitfield Welding WB-1 6.27 $364 $176