Cutting & forming Commercial
Move to
Value
$10,560
sell to Ridgeline Land Co
Estimated cost
$7,022
est. margin 33.5%
Cost to date
$594
forecast $7,022
Forecast return
$3,538
margin 33.5% · ROI 50.4%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $5,240 reserved now | $5,240 | $0 | — |
| Labour 5.4 h logged of 14.7 h estimated | $909 | $247 | $662 |
| Machine time at the machine's hourly rate | $873 | $347 | $526 |
| Galvanising (outside) none on this item | $0 | $0 | $0 |
| Total | $7,022 | $594 |
Job detailsT-23-014 →
- Item
- CB-POST-MON Colorbond post 2400 — Monument
- Quantity
- 440
- Finish
- Colorbond (pre-finished)
- Project
- T-23-014 — Ellenbrook Ridge — Stages 6–9
- Customer
- Ridgeline Land Co
- Machine
- RF-02
- Start / due
- 05 Nov 2026 → 12 Nov 2026
Material — allocated from stock
Hours logged5.4 h · labour $247 · machine $347
| Date | Who | Operation | Machine | Hours | Labour | Machine | |
|---|---|---|---|---|---|---|---|
| 05 Nov 2026 | Liam O'Connor | Roll forming | RF-02 | 1 | $56 | $85 | |
| 05 Nov 2026 | Sipho Ndlovu | Packing & dispatch | — | 1.32 | $71 | $0 | |
| 05 Nov 2026 | Josh Taylor | Roll forming | RF-02 | 3.08 | $120 | $262 | |