Fence Corporation

FJ-26-0401 · 440 × CB-POST-MON

Colorbond post 2400 — Monument · T-23-014 Ellenbrook Ridge — Stages 6–9
Xero · synced 09:14 Demo 05 Nov 2026
Cutting & forming Commercial
Move to
Value
$10,560
sell to Ridgeline Land Co
Estimated cost
$7,022
est. margin 33.5%
Cost to date
$594
forecast $7,022
Forecast return
$3,538
margin 33.5% · ROI 50.4%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $5,240 reserved now
$5,240$0 —
Labour
5.4 h logged of 14.7 h estimated
$909$247 $662
Machine time
at the machine's hourly rate
$873$347 $526
Galvanising (outside)
none on this item
$0$0 $0
Total$7,022$594
Job detailsT-23-014 →
Item
CB-POST-MON Colorbond post 2400 — Monument
Quantity
440
Finish
Colorbond (pre-finished)
Project
T-23-014 — Ellenbrook Ridge — Stages 6–9
Customer
Ridgeline Land Co
Machine
RF-02
Start / due
05 Nov 2026 → 12 Nov 2026
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
CBC-MON Colorbond coil 0.42 BMT — Monument 2,024 kg 2,024 — $2.35 $4,756
PC50 Post cap 50 × 50 440 ea 440 — $1.10 $484
Hours logged5.4 h · labour $247 · machine $347
DateWhoOperationMachineHoursLabourMachine
05 Nov 2026 Liam O'Connor Roll forming RF-02 1 $56 $85
05 Nov 2026 Sipho Ndlovu Packing & dispatch — 1.32 $71 $0
05 Nov 2026 Josh Taylor Roll forming RF-02 3.08 $120 $262