Cutting & forming Commercial
Move to
Value
$32,800
sell to Ridgeline Land Co
Estimated cost
$23,581
est. margin 28.1%
Cost to date
$1,916
forecast $23,581
Forecast return
$9,219
margin 28.1% · ROI 39.1%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $19,074 reserved now | $19,074 | $0 | — |
| Labour 18.5 h logged of 40 h estimated | $2,480 | $976 | $1,504 |
| Machine time at the machine's hourly rate | $2,027 | $941 | $1,086 |
| Galvanising (outside) none on this item | $0 | $0 | $0 |
| Total | $23,581 | $1,916 |
Job detailsT-23-014 →
- Item
- CB-PNL-MON Colorbond panel 2.35 × 1.8 — Monument
- Quantity
- 400
- Finish
- Colorbond (pre-finished)
- Project
- T-23-014 — Ellenbrook Ridge — Stages 6–9
- Customer
- Ridgeline Land Co
- Machine
- RF-01
- Start / due
- 04 Nov 2026 → 11 Nov 2026
Material — allocated from stock
Hours logged18.5 h · labour $976 · machine $941
| Date | Who | Operation | Machine | Hours | Labour | Machine | |
|---|---|---|---|---|---|---|---|
| 05 Nov 2026 | Josh Taylor | Packing & dispatch | — | 3 | $117 | $0 | |
| 05 Nov 2026 | Liam O'Connor | Roll forming | RF-01 | 3.5 | $196 | $333 | |
| 04 Nov 2026 | Liam O'Connor | Packing & dispatch | — | 1 | $56 | $0 | |
| 04 Nov 2026 | Sipho Ndlovu | Packing & dispatch | — | 4.6 | $248 | $0 | |
| 04 Nov 2026 | Liam O'Connor | Roll forming | RF-01 | 0.57 | $32 | $54 | |
| 04 Nov 2026 | Liam O'Connor | Roll forming | RF-01 | 5.83 | $326 | $554 | |