FJ-26-0400 · 400 × CB-PNL-MON

Colorbond panel 2.35 × 1.8 — Monument · T-23-014 Ellenbrook Ridge — Stages 6–9
Xero · synced 09:14 Demo 05 Nov 2026
Cutting & forming Commercial
Move to
Value
$32,800
sell to Ridgeline Land Co
Estimated cost
$23,581
est. margin 28.1%
Cost to date
$1,916
forecast $23,581
Forecast return
$9,219
margin 28.1% · ROI 39.1%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $19,074 reserved now
$19,074$0 —
Labour
18.5 h logged of 40 h estimated
$2,480$976 $1,504
Machine time
at the machine's hourly rate
$2,027$941 $1,086
Galvanising (outside)
none on this item
$0$0 $0
Total$23,581$1,916
Job detailsT-23-014 →
Item
CB-PNL-MON Colorbond panel 2.35 × 1.8 — Monument
Quantity
400
Finish
Colorbond (pre-finished)
Project
T-23-014 — Ellenbrook Ridge — Stages 6–9
Customer
Ridgeline Land Co
Machine
RF-01
Start / due
04 Nov 2026 → 11 Nov 2026
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
CBC-MON Colorbond coil 0.42 BMT — Monument 7,800 kg 7,800 — $2.35 $18,330
RV48 Rivet 4.8 mm sealed 2,400 ea 2,400 — $0.04 $96
TEK20 Tek screw 12-14 × 20 hex, class 3 7,200 ea 7,200 — $0.09 $648
Hours logged18.5 h · labour $976 · machine $941
DateWhoOperationMachineHoursLabourMachine
05 Nov 2026 Josh Taylor Packing & dispatch — 3 $117 $0
05 Nov 2026 Liam O'Connor Roll forming RF-01 3.5 $196 $333
04 Nov 2026 Liam O'Connor Packing & dispatch — 1 $56 $0
04 Nov 2026 Sipho Ndlovu Packing & dispatch — 4.6 $248 $0
04 Nov 2026 Liam O'Connor Roll forming RF-01 0.57 $32 $54
04 Nov 2026 Liam O'Connor Roll forming RF-01 5.83 $326 $554