CI-26-018 · Kwinana Bulk Terminal — perimeter security 2.1 km

Westshore Port Services · Civil & Industrial · Quoted project
Xero · synced 09:14 Demo 05 Nov 2026
FabricatingCivil & Industrial From Q-26-0418 17 Aug 2026 → 11 Dec 2026 · Dehan Pretorius
Contract
$486,000
ex GST
Invoiced to date
$113,850
23% of contract
Fabrication
$164,430
5 fab jobs · cost $102,183
Fabrication return
$62,247
margin 37.9%
Project return
$285,817
contract less fab $102,183 + install $98,000
Fab jobs for this project$60,312 spent to date
Fab jobItemQtyStageDueMaterialValueCostReturnMargin
FJ-26-0413SLD-GATE-6
Cantilever sliding gate 6.0 × 2.1, HDG
1Planned 2 Decnot reserved $3,650$1,948$1,70246.6%
FJ-26-0397SEC-POST-3000
Security post SHS 75 × 3000, base plate & cap, HDG
170Welding & assembly 3 NovAllocated $28,560$17,853$10,70737.5%
FJ-26-0396SEC-358-2418
358 security mesh panel 2.4 × 1.8, framed, HDG
160Finishing 9 NovAllocated $47,200$29,081$18,11938.4%
FJ-26-0385SEC-POST-3000
Security post SHS 75 × 3000, base plate & cap, HDG
190Complete 9 Octissued $31,920$19,679$12,24138.4%
FJ-26-0384SEC-358-2418
358 security mesh panel 2.4 × 1.8, framed, HDG
180Complete 6 Octissued $53,100$33,622$19,47836.7%
Invoices & claimsAll invoices
INV-010860
30 Oct
Kwinana Bulk Terminal — claim 2 (install 0.62 km)Sent$28,830
INV-010859
9 Oct
Kwinana Bulk Terminal — claim 1 (fabrication to 9 Oct)Paid$85,020
Purchase orders
PO-26-0527Metalcorp SteelPart received$15,304
PO-26-0525WA Mesh & WireReceived$21,120
PO-26-0516WA Mesh & WireReceived$47,100
PO-26-0515Metalcorp SteelReceived$26,920