Fence Corporation

FJ-26-0413 · 1 × SLD-GATE-6

Cantilever sliding gate 6.0 × 2.1, HDG · CI-26-018 Kwinana Bulk Terminal — perimeter security 2.1 km
Xero · synced 09:14 Demo 05 Nov 2026
Planned Civil & Industrial
Move to
Value
$3,650
sell to Westshore Port Services
Estimated cost
$1,948
est. margin 46.6%
Cost to date
$0
forecast $1,948
Forecast return
$1,702
margin 46.6% · ROI 87.4%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $0 reserved now
$1,204$0 —
Labour
0 h logged of 6 h estimated
$372$0 $372
Machine time
at the machine's hourly rate
$112$0 $112
Galvanising (outside)
Industrial Galvanizers — billed per load
$260$0 $260
Total$1,948$0
Job detailsCI-26-018 →
Item
SLD-GATE-6 Cantilever sliding gate 6.0 × 2.1, HDG
Quantity
1
Finish
Hot-dip galvanised
Project
CI-26-018 — Kwinana Bulk Terminal — perimeter security 2.1 km
Customer
Westshore Port Services
Machine
WB-1
Start / due
19 Nov 2026 → 02 Dec 2026
Notes
Main entry gate — 7.5 m clear opening, confirm with Westshore before cutting.
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
Nothing reserved yet — move the job to Material allocated to reserve its bill of materials.
Hours logged0 h · labour $0 · machine $0
DateWhoOperationMachineHoursLabourMachine