Planned Civil & Industrial
Move to
Value
$3,650
sell to Westshore Port Services
Estimated cost
$1,948
est. margin 46.6%
Cost to date
$0
forecast $1,948
Forecast return
$1,702
margin 46.6% · ROI 87.4%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $0 reserved now | $1,204 | $0 | — |
| Labour 0 h logged of 6 h estimated | $372 | $0 | $372 |
| Machine time at the machine's hourly rate | $112 | $0 | $112 |
| Galvanising (outside) Industrial Galvanizers — billed per load | $260 | $0 | $260 |
| Total | $1,948 | $0 |
Job detailsCI-26-018 →
- Item
- SLD-GATE-6 Cantilever sliding gate 6.0 × 2.1, HDG
- Quantity
- 1
- Finish
- Hot-dip galvanised
- Project
- CI-26-018 — Kwinana Bulk Terminal — perimeter security 2.1 km
- Customer
- Westshore Port Services
- Machine
- WB-1
- Start / due
- 19 Nov 2026 → 02 Dec 2026
- Notes
- Main entry gate — 7.5 m clear opening, confirm with Westshore before cutting.
Material — allocated from stock
| Material | Required | Allocated | Short | Unit cost | Value reserved |
|---|---|---|---|---|---|
| Nothing reserved yet — move the job to Material allocated to reserve its bill of materials. | |||||
Hours logged0 h · labour $0 · machine $0
| Date | Who | Operation | Machine | Hours | Labour | Machine |
|---|
Nothing here yet — use “Log time” to create the first one.