CI-26-025 · Roe Highway shared path — handrail & bollards

Metro Civil Group · Civil & Industrial · Quoted project
Xero · synced 09:14 Demo 05 Nov 2026
FabricatingCivil & Industrial From Q-26-0433 28 Sep 2026 → 04 Dec 2026 · Dehan Pretorius
Contract
$96,000
ex GST
Invoiced to date
$0
0% of contract
Fabrication
$46,455
3 fab jobs · cost $30,108
Fabrication return
$16,347
margin 35.2%
Project return
$44,892
contract less fab $30,108 + install $21,000
Fab jobs for this project$6,977 spent to date
Fab jobItemQtyStageDueMaterialValueCostReturnMargin
FJ-26-0412HR-GALV-3
Handrail 3.0 m CHS 48.3, two-rail, HDG
30Planned 27 Novnot reserved $10,350$7,271$3,07929.7%
FJ-26-0395BOL-114
Bollard CHS 114 × 1200 in-ground, HDG + cap
85Finishing 10 NovAllocated $14,025$7,324$6,70147.8%
FJ-26-0394HR-GALV-3
Handrail 3.0 m CHS 48.3, two-rail, HDG
64QC & dispatch 6 NovAllocated $22,080$15,512$6,56829.7%
Invoices & claimsAll invoices
INV-010867
5 Nov
Roe Highway shared path — claim 1 (materials on site)Draft$22,080
Purchase orders
PO-26-0524Metalcorp SteelReceived$11,700