Contract
$96,000
ex GST
Invoiced to date
$0
0% of contract
Fabrication
$46,455
3 fab jobs · cost $30,108
Fabrication return
$16,347
margin 35.2%
Project return
$44,892
contract less fab $30,108 + install $21,000
Fab jobs for this project$6,977 spent to date
| Fab job | Item | Qty | Stage | Due | Material | Value | Cost | Return | Margin |
|---|---|---|---|---|---|---|---|---|---|
| FJ-26-0412 | HR-GALV-3 Handrail 3.0 m CHS 48.3, two-rail, HDG | 30 | Planned | 27 Nov | not reserved | $10,350 | $7,271 | $3,079 | 29.7% |
| FJ-26-0395 | BOL-114 Bollard CHS 114 × 1200 in-ground, HDG + cap | 85 | Finishing | 10 Nov | Allocated | $14,025 | $7,324 | $6,701 | 47.8% |
| FJ-26-0394 | HR-GALV-3 Handrail 3.0 m CHS 48.3, two-rail, HDG | 64 | QC & dispatch | 6 Nov | Allocated | $22,080 | $15,512 | $6,568 | 29.7% |
Invoices & claimsAll invoices
| INV-010867 5 Nov | Roe Highway shared path — claim 1 (materials on site) | Draft | $22,080 |
Purchase orders
| PO-26-0524 | Metalcorp Steel | Received | $11,700 |