Value
$22,080
sell to Metro Civil Group
Estimated cost
$15,512
est. margin 29.7%
Cost to date
$5,985
forecast $15,512
Forecast return
$6,568
margin 29.7% · ROI 42.3%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $9,208 reserved now | $9,208 | $0 | — |
| Labour 45.1 h logged of 48 h estimated | $2,976 | $2,719 | $257 |
| Machine time at the machine's hourly rate | $896 | $842 | $54 |
| Galvanising (outside) Industrial Galvanizers — billed per load | $2,432 | $2,423 | $9 |
| Total | $15,512 | $5,985 |
Job detailsCI-26-025 →
- Item
- HR-GALV-3 Handrail 3.0 m CHS 48.3, two-rail, HDG
- Quantity
- 64
- Finish
- Hot-dip galvanised
- Project
- CI-26-025 — Roe Highway shared path — handrail & bollards
- Customer
- Metro Civil Group
- Machine
- WB-1
- Start / due
- 21 Oct 2026 → 06 Nov 2026
Material — allocated from stock
Hours logged45.1 h · labour $2,719 · machine $842
| Date | Who | Operation | Machine | Hours | Labour | Machine | |
|---|---|---|---|---|---|---|---|
| 03 Nov 2026 | Sipho Ndlovu | Galv prep & touch-up | — | 2.47 | $133 | $0 | |
| 02 Nov 2026 | Sipho Ndlovu | Galv prep & touch-up | — | 5.02 | $271 | $0 | |
| 30 Oct 2026 | Sipho Ndlovu | Galv prep & touch-up | — | 7.55 | $408 | $0 | |
| 29 Oct 2026 | Jaco Botha | Welding | WB-1 | 3.43 | $226 | $96 | |
| 28 Oct 2026 | Jaco Botha | Welding | WB-1 | 6.16 | $407 | $172 | |
| 27 Oct 2026 | Ben Whitfield | Welding | WB-1 | 6.96 | $404 | $195 | |
| 26 Oct 2026 | Jaco Botha | Welding | WB-1 | 2.11 | $139 | $59 | |
| 23 Oct 2026 | Ben Whitfield | Welding | WB-1 | 2.49 | $144 | $70 | |
| 22 Oct 2026 | Amir | Welding | WB-1 | 3.23 | $239 | $90 | |
| 21 Oct 2026 | Tama Ngata | Welding | WB-1 | 5.7 | $348 | $160 | |