Fence Corporation

FJ-26-0394 · 64 × HR-GALV-3

Handrail 3.0 m CHS 48.3, two-rail, HDG · CI-26-025 Roe Highway shared path — handrail & bollards
Xero · synced 09:14 Demo 05 Nov 2026
QC & dispatch Civil & Industrial
Move to
Value
$22,080
sell to Metro Civil Group
Estimated cost
$15,512
est. margin 29.7%
Cost to date
$5,985
forecast $15,512
Forecast return
$6,568
margin 29.7% · ROI 42.3%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $9,208 reserved now
$9,208$0 —
Labour
45.1 h logged of 48 h estimated
$2,976$2,719 $257
Machine time
at the machine's hourly rate
$896$842 $54
Galvanising (outside)
Industrial Galvanizers — billed per load
$2,432$2,423 $9
Total$15,512$5,985
Job detailsCI-26-025 →
Item
HR-GALV-3 Handrail 3.0 m CHS 48.3, two-rail, HDG
Quantity
64
Finish
Hot-dip galvanised
Project
CI-26-025 — Roe Highway shared path — handrail & bollards
Customer
Metro Civil Group
Machine
WB-1
Start / due
21 Oct 2026 → 06 Nov 2026
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
BP200 Base plate 200 × 200 × 10 (laser cut) 128 ea 128 — $14.50 $1,856
CHS48 CHS 48.3 × 3.2 galv 614.4 m 614.4 — $11.80 $7,250
WW09 Welding wire ER70S-6 0.9 mm 16 kg 16 — $6.40 $102
Hours logged45.1 h · labour $2,719 · machine $842
DateWhoOperationMachineHoursLabourMachine
03 Nov 2026 Sipho Ndlovu Galv prep & touch-up — 2.47 $133 $0
02 Nov 2026 Sipho Ndlovu Galv prep & touch-up — 5.02 $271 $0
30 Oct 2026 Sipho Ndlovu Galv prep & touch-up — 7.55 $408 $0
29 Oct 2026 Jaco Botha Welding WB-1 3.43 $226 $96
28 Oct 2026 Jaco Botha Welding WB-1 6.16 $407 $172
27 Oct 2026 Ben Whitfield Welding WB-1 6.96 $404 $195
26 Oct 2026 Jaco Botha Welding WB-1 2.11 $139 $59
23 Oct 2026 Ben Whitfield Welding WB-1 2.49 $144 $70
22 Oct 2026 Amir Welding WB-1 3.23 $239 $90
21 Oct 2026 Tama Ngata Welding WB-1 5.7 $348 $160