Value
$14,025
sell to Metro Civil Group
Estimated cost
$7,324
est. margin 47.8%
Cost to date
$992
forecast $7,324
Forecast return
$6,701
margin 47.8% · ROI 91.5%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $4,131 reserved now | $4,131 | $0 | — |
| Labour 13.3 h logged of 17 h estimated | $1,054 | $777 | $277 |
| Machine time at the machine's hourly rate | $269 | $215 | $54 |
| Galvanising (outside) Industrial Galvanizers — billed per load | $1,870 | $0 | $1,870 |
| Total | $7,324 | $992 |
Job detailsCI-26-025 →
- Item
- BOL-114 Bollard CHS 114 × 1200 in-ground, HDG + cap
- Quantity
- 85
- Finish
- Hot-dip galvanised
- Project
- CI-26-025 — Roe Highway shared path — handrail & bollards
- Customer
- Metro Civil Group
- Machine
- BS-01
- Start / due
- 26 Oct 2026 → 10 Nov 2026
- Notes
- At Industrial Galvanizers — back Mon.
Material — allocated from stock
Hours logged13.3 h · labour $777 · machine $215
| Date | Who | Operation | Machine | Hours | Labour | Machine | |
|---|---|---|---|---|---|---|---|
| 02 Nov 2026 | Josh Taylor | Galv prep & touch-up | — | 0.96 | $37 | $0 | |
| 28 Oct 2026 | Ben Whitfield | Welding | — | 6.7 | $389 | $0 | |
| 26 Oct 2026 | Ravi Sharma | Cutting | BS-01 | 5.66 | $351 | $215 | |