Fence Corporation

FJ-26-0395 · 85 × BOL-114

Bollard CHS 114 × 1200 in-ground, HDG + cap · CI-26-025 Roe Highway shared path — handrail & bollards
Xero · synced 09:14 Demo 05 Nov 2026
Finishing Civil & Industrial
Move to
Value
$14,025
sell to Metro Civil Group
Estimated cost
$7,324
est. margin 47.8%
Cost to date
$992
forecast $7,324
Forecast return
$6,701
margin 47.8% · ROI 91.5%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $4,131 reserved now
$4,131$0 —
Labour
13.3 h logged of 17 h estimated
$1,054$777 $277
Machine time
at the machine's hourly rate
$269$215 $54
Galvanising (outside)
Industrial Galvanizers — billed per load
$1,870$0 $1,870
Total$7,324$992
Job detailsCI-26-025 →
Item
BOL-114 Bollard CHS 114 × 1200 in-ground, HDG + cap
Quantity
85
Finish
Hot-dip galvanised
Project
CI-26-025 — Roe Highway shared path — handrail & bollards
Customer
Metro Civil Group
Machine
BS-01
Start / due
26 Oct 2026 → 10 Nov 2026
Notes
At Industrial Galvanizers — back Mon.
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
CHS114 CHS 114.3 × 4.8 102 m 102 — $38.50 $3,927
PC75 Post cap 75 × 75 85 ea 85 — $2.40 $204
Hours logged13.3 h · labour $777 · machine $215
DateWhoOperationMachineHoursLabourMachine
02 Nov 2026 Josh Taylor Galv prep & touch-up — 0.96 $37 $0
28 Oct 2026 Ben Whitfield Welding — 6.7 $389 $0
26 Oct 2026 Ravi Sharma Cutting BS-01 5.66 $351 $215