ActiveCommercial 02 Sep 2024 → 31 Mar 2027 · Craig Hollis
Contract
$1,460,000
420 lots under tender
Invoiced to date
$671,189
46% of contract
Fabrication
$55,240
3 fab jobs · cost $39,390
Fabrication return
$15,850
margin 28.7%
Fab jobs for this project$16,597 spent to date
| Fab job | Item | Qty | Stage | Due | Material | Value | Cost | Return | Margin |
|---|---|---|---|---|---|---|---|---|---|
| FJ-26-0404 | CB-POST-WG Colorbond post 2400 — Woodland Grey | 320 | Material allocated | 17 Nov | Allocated | $7,680 | $5,107 | $2,573 | 33.5% |
| FJ-26-0403 | CB-PNL-WG Colorbond panel 2.35 × 1.8 — Woodland Grey | 300 | Material allocated | 17 Nov | Allocated | $24,600 | $17,686 | $6,915 | 28.1% |
| FJ-26-0383 | CB-PNL-WG Colorbond panel 2.35 × 1.8 — Woodland Grey | 280 | Complete | 29 Sep | issued | $22,960 | $16,597 | $6,363 | 27.7% |
Invoices & claimsAll invoices
| INV-010846 31 Oct | Alkimos Shores — Precinct 3 — October lot claim | Sent | $16,469 |
| INV-010845 30 Sep | Alkimos Shores — Precinct 3 — September lot claim | Paid | $11,624 |
| INV-010844 31 Aug | Alkimos Shores — Precinct 3 — lot claims to 31 Aug (185 lots) | Paid | $643,095 |
Purchase orders
| PO-26-0530 | BlueScope Distribution | Sent | $28,550 |