Fence Corporation

FJ-26-0411 · 8 × FLX-LND

Flexistep landing module 1200 × 1200 · FX-26-010 Flexistep supply — Broome camp
Xero · synced 09:14 Demo 05 Nov 2026
Planned Fabrication
Move to
Value
$11,120
sell to Kimberley Site Accommodation
Estimated cost
$5,404
est. margin 51.4%
Cost to date
$0
forecast $5,404
Forecast return
$5,716
margin 51.4% · ROI 105.8%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $0 reserved now
$3,996$0 —
Labour
0 h logged of 10.7 h estimated
$661$0 $661
Machine time
at the machine's hourly rate
$187$0 $187
Galvanising (outside)
Industrial Galvanizers — billed per load
$560$0 $560
Total$5,404$0
Job detailsFX-26-010 →
Item
FLX-LND Flexistep landing module 1200 × 1200
Quantity
8
Finish
Hot-dip galvanised
Project
FX-26-010 — Flexistep supply — Broome camp
Customer
Kimberley Site Accommodation
Machine
WB-1
Start / due
12 Nov 2026 → 24 Nov 2026
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
Nothing reserved yet — move the job to Material allocated to reserve its bill of materials.
Hours logged0 h · labour $0 · machine $0
DateWhoOperationMachineHoursLabourMachine
Nothing here yet — use “Log time” to create the first one.