Planned Fabrication
Move to
Value
$28,400
sell to Pilbara Camps & Modular
Estimated cost
$11,728
est. margin 58.7%
Cost to date
$0
forecast $11,728
Forecast return
$16,672
margin 58.7% · ROI 142.2%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $0 reserved now | $8,098 | $0 | — |
| Labour 0 h logged of 28.3 h estimated | $1,757 | $0 | $1,757 |
| Machine time at the machine's hourly rate | $513 | $0 | $513 |
| Galvanising (outside) Industrial Galvanizers — billed per load | $1,360 | $0 | $1,360 |
| Total | $11,728 | $0 |
Job detailsFX-26-007 →
- Item
- FLX-K3 Flexistep stair kit — 3 step
- Quantity
- 20
- Finish
- Hot-dip galvanised
- Project
- FX-26-007 — Flexistep supply — Pilbara camps
- Customer
- Pilbara Camps & Modular
- Machine
- WB-1
- Start / due
- 16 Nov 2026 → 27 Nov 2026
Material — allocated from stock
| Material | Required | Allocated | Short | Unit cost | Value reserved |
|---|---|---|---|---|---|
| Nothing reserved yet — move the job to Material allocated to reserve its bill of materials. | |||||
Hours logged0 h · labour $0 · machine $0
| Date | Who | Operation | Machine | Hours | Labour | Machine |
|---|
Nothing here yet — use “Log time” to create the first one.