Fence Corporation

T-24-027 · Byford Meadows — Stage 12

Southern Grove Developments · Commercial · Tender
Xero · synced 09:14 Demo 05 Nov 2026
ActiveCommercial 11 Nov 2024 → 18 Dec 2026 · Craig Hollis
Contract
$860,000
260 lots under tender
Invoiced to date
$780,166
91% of contract
Fabrication
$37,720
2 fab jobs · cost $27,080
Fabrication return
$10,640
margin 28.2%
Lots on the board
7/22
Fab jobs for this project$12,932 spent to date
Fab jobItemQtyStageDueMaterialValueCostReturnMargin
FJ-26-0410CB-PNL-BAS
Colorbond panel 2.35 × 1.8 — Basalt
240Planned 23 Novnot reserved $19,680$14,148$5,53228.1%
FJ-26-0391CB-PNL-BAS
Colorbond panel 2.35 × 1.8 — Basalt
220Complete 30 Octissued $18,040$12,932$5,10828.3%
Invoices & claimsAll invoices
INV-010849
31 Oct
Byford Meadows — Stage 12 — October lot claimSent$15,981
INV-010848
30 Sep
Byford Meadows — Stage 12 — September lot claimOverdue$10,032
INV-010847
31 Aug
Byford Meadows — Stage 12 — lot claims to 31 Aug (228 lots)Paid$754,153
Purchase orders
No project POs.