ActiveFabrication 01 Oct 2026 → 31 Dec 2026 · Amir
Contract
$29,430
ex GST
Invoiced to date
$0
0% of contract
Fabrication
$29,430
2 fab jobs · cost $26,971
Fabrication return
$2,459
margin 8.4%
Project return
$2,459
contract less fab $26,971 + install $0
Fab jobs for this project$15,774 spent to date
| Fab job | Item | Qty | Stage | Due | Material | Value | Cost | Return | Margin |
|---|---|---|---|---|---|---|---|---|---|
| FJ-26-0409 | TMP-PNL-2421 Temporary fence panel 2.4 × 2.1 (sacrificial) | 120 | Planned | 26 Nov | not reserved | $13,080 | $11,197 | $1,883 | 14.4% |
| FJ-26-0390 | TMP-PNL-2421 Temporary fence panel 2.4 × 2.1 (sacrificial) | 150 | Complete | 27 Oct | issued | $16,350 | $15,774 | $576 | 3.5% |
Invoices & claimsAll invoices
| No invoices yet. |
Purchase orders