Fence Corporation

FJ-26-0414 · 320 × CB-PNL-MON

Colorbond panel 2.35 × 1.8 — Monument · T-25-006 Baldivis Parks — Stage 4
Xero · synced 09:14 Demo 05 Nov 2026
Planned Commercial
Move to
Value
$26,240
sell to Parkstone Estates
Estimated cost
$18,865
est. margin 28.1%
Cost to date
$0
forecast $18,865
Forecast return
$7,375
margin 28.1% · ROI 39.1%
Variance to estimate
$0
under estimate
Estimate against actual
CostEstimateTo dateVariance
Steel & materials
issued on completion — $0 reserved now
$15,259$0 —
Labour
0 h logged of 32 h estimated
$1,984$0 $1,984
Machine time
at the machine's hourly rate
$1,621$0 $1,621
Galvanising (outside)
none on this item
$0$0 $0
Total$18,865$0
Job detailsT-25-006 →
Item
CB-PNL-MON Colorbond panel 2.35 × 1.8 — Monument
Quantity
320
Finish
Colorbond (pre-finished)
Project
T-25-006 — Baldivis Parks — Stage 4
Customer
Parkstone Estates
Machine
RF-01
Start / due
23 Nov 2026 → 30 Nov 2026
Material — allocated from stock
MaterialRequiredAllocatedShortUnit costValue reserved
Nothing reserved yet — move the job to Material allocated to reserve its bill of materials.
Hours logged0 h · labour $0 · machine $0
DateWhoOperationMachineHoursLabourMachine
Nothing here yet — use “Log time” to create the first one.