Material allocated 1 material short Civil & Industrial
Move to
Value
$15,340
sell to Northgate Constructions
Estimated cost
$9,451
est. margin 38.4%
Cost to date
$0
forecast $9,451
Forecast return
$5,889
margin 38.4% · ROI 62.3%
Variance to estimate
$0
under estimate
Estimate against actual
| Cost | Estimate | To date | Variance |
|---|---|---|---|
| Steel & materials issued on completion — $3,893 reserved now | $6,005 | $0 | — |
| Labour 0 h logged of 24.3 h estimated | $1,505 | $0 | $1,505 |
| Machine time at the machine's hourly rate | $485 | $0 | $485 |
| Galvanising (outside) Industrial Galvanizers — billed per load | $1,456 | $0 | $1,456 |
| Total | $9,451 | $0 |
Job detailsCI-26-031 →
- Item
- SEC-358-2418 358 security mesh panel 2.4 × 1.8, framed, HDG
- Quantity
- 52
- Finish
- Hot-dip galvanised
- Project
- CI-26-031 — Forrestfield school — 358 perimeter & gates
- Customer
- Northgate Constructions
- Machine
- WB-1
- Start / due
- 11 Nov 2026 → 25 Nov 2026
Material — allocated from stock
Hours logged0 h · labour $0 · machine $0
| Date | Who | Operation | Machine | Hours | Labour | Machine |
|---|
Nothing here yet — use “Log time” to create the first one.